task force issues final report

Final report of Rupp task force envisions $300 million project with many sources of financing

Proposal envisions somenew facilities by 2016Rupp Arena: Renovation will maintain 'gold standard ... expected' of facilityThe cost: Up to $300 million needed; funding ideas but no specifics offered

bfortune@herald-leader.comFebruary 1, 2012 

  • Recommendations

    ■ "Free Rupp Arena." Renovate it, maintain its historic character, make it a stand-alone structure.

    ■ New, bigger convention area.

    ■ Small performing arts center, arts education space, outdoor gathering/performance area, visual arts space.

    ■ Town Branch Commons, a thread of public space from the Distillery District to the East End, generally following Town Branch Creek.

    ■ Retail shops near Rupp Arena, facing Main Street and along Town Branch Commons Park, and a CatWalk between Avenue of Champions and the arena.

    ■ Parking garage and transportation hub for buses and rail.

    Potential funding sources

    ■ Revenue from premium seating, sale of stock, naming rights, advertising, concert/event promotions, concessions and parking.

    ■ Local and state governments and federal grants.

    ■ Private fund-raising.

    ■ Tax credits, including establishment of a tax increment financing, or TIF, district to support infrastructure and civic facilities.

    Proposed timetable

    April: Hire project director and project planner at Lexington Center.

    June: Solicit and select program manager and professional consultants.

    October: Complete economic and financial feasibility studies.

    November: Solicit and select design and construction teams.

    June 2013: Complete concept design.

    December 2013: Complete schematic design, cost estimates.

    Early 2014: Begin site work/demolition work.

    August 2014: Issue bonds, begin major construction.

    Spring 2014-Fall 2016: Construct Lexington Center.

    Spring 2015-Summer 2017: Renovate Rupp Arena and build Town Branch Park.

  • Goals for Rupp Arena

    ■ Suites

    ■ Club/loge seats

    ■ All chair-back seats

    ■ Maintain seating capacity

    ■ Home games continued without displacement

    ■ New support space for media, team locker rooms and player families

    ■ New technology

    ■ New sound system

    ■ Entertainment space for the city, UK president, athletics director

The Arena, Arts and Entertainment District Task Force's final report envisions a $250 million to $300 million "transformation" of Lexington Center, including Rupp Arena, the Lexington Convention Center, the Civic Center Shoppes and immediate environs, but it does not outline a specific plan to pay for the huge project.

The report, issued Tuesday, said building a new Rupp Arena would not be economically feasible.

As previously reported, the task force proposes a major renovation of the city-owned arena rather than replacing the 24,000-seat home of the University of Kentucky Wildcats.

The 35-year-old arena would be substantially renovated to make it "the center of the expanded downtown."

"The renovation will maintain the historic character while maintaining the gold standard that is expected of Rupp Arena, both architecturally and symbolically," the report said.

The Lexington Convention Center, including the Civic Center Shoppes, would be removed. A new convention center made up of a cluster of buildings on a campuslike setting would be built immediately west of Rupp.

The Civic Center Shoppes would be moved into several small retail buildings along West Main Street.

The 46-acre arts and entertainment district would be primarily in an area bounded by Oliver Lewis Way, Broadway, and Short and High streets.

The task force also recommended the district include a small performing arts center, a school for the arts, an outdoor gathering and performance space, housing, a parking garage and new areas for retail. Town Branch, which runs through downtown in an underground culvert, would be brought to the surface.

"Now is where the hard work starts," said Gary Bates, design-team leader from the Norway-based firm Space Group, which was hired in August to develop a master plan for the proposed district.

"Now we really need to go from a vision to start implementing that vision. We don't have a lot of time if we want to meet the 2018 milestone," said Bates, a former basketball player who grew up in Virginia and taught at UK.

UK has a contract with Lexington Center to play its men's basketball games in Rupp Arena through 2018.

Most critical at this point, task force members said, is lining up financing.

If financing is found, phased demolition and construction of the civic center and Rupp Arena could start as early as 2014.

"This important project will require a mix of local, state and private funding for construction," the report said.

The finance committee, chaired by Central Bank president Luther Deaton, has identified 14 potential funding sources, including revenue from naming rights of the arena, premium seating, advertising, sponsorships, concert and event promotions, concessions, stock offerings, state road funds, state tourism tax incentives, tax increment financing and new market tax credits.

The next step will be "to get our arms around all the revenue streams. We'll have to ... confirm those" streams, said task force chairman Brent Rice.

Rice said there was "tremendous retail opportunity (and) tremendous opportunity with the technology changes inside Rupp. We have to have a very detailed, well-studied business plan going forward so we understand all components."

Gov. Steve Beshear put $3.5 million in his recent state budget proposal for the project, contingent on a Lexington match of $1.5 million.

Mayor Jim Gray said the $5 million would be enough to hire a program manager and begin design, engineering and finance work.

Gray had planned to meet Tuesday afternoon in Frankfort with Central Kentucky lawmakers to defend the $3.5 million. But the meeting had to be postponed because other House business interfered.

The Green Bay Packers' model of selling stock to fans to raise money to renovate Lambeau Field also will be looked at, Rice said. "That's an option. The Packers raised almost $62 million. That needs to be looked at. ... We think there's an opportunity there."

Bates said that last week in Scandinavia some people approached him and said they loved basketball and asked how could they get involved in the Rupp Arena project, meaning on a financial level.

"It completely shocked me ...I didn't anticipate (Rupp Arena) to have such a resonating interest outside of Kentucky. That has been the biggest surprise," Bates said. Asked whether he thought selling stock to renovate Rupp could happen, he said, "Absolutely, it can happen."

A critical factor in the overall financial picture is to have financing in place so that when the economy changes, the project will be shovel-ready, Rice said.

Gray told task force members that not everyone would get behind plans for the district. But he said, "A big part of the democratic process is the dissenting voice. ... Things are not always sanitized and sweetness and light. We know as we go down this road there will be ... many points of view, and we will accommodate those."

UK President Eli Capilouto issued a statement Tuesday afternoon in response to the report.

"Our position has not changed," he said. "Our steadfast focus has been— and will continue to be — the revitalization of our campus core. We have concerns about anything that competes for state dollars with that focus.

"Revitalizing our campus represents the best way we can honor the Kentucky Promise of ensuring the best possible undergraduate education for the commonwealth's students and future leaders as well as the kind of research that addresses the state's challenges.

"Everyone needs to clearly understand the specifics of what the proposed Rupp Arena, Arts and Entertainment District will cost and who would ultimately pay for it."

Lexington Herald-Leader is pleased to provide this opportunity to share information, experiences and observations about what's in the news. Some of the comments may be reprinted elsewhere in the site or in the newspaper. We encourage lively, open debate on the issues of the day, and ask that you refrain from profanity, hate speech, personal comments and remarks that are off point. Thank you for taking the time to offer your thoughts.

Commenting FAQs | Terms of Service